Why train station by Bristol’s new arena has been delayed
A planned train station by the new arena in Filton will not open until 2026 after delays were blamed on several design changes.
The station was initially due to open next year, before the YTL Arena opens in 2024, as a key part of the transport plan to get people to concerts.
North Filton station is one of three new stations opening over the next few years, with services running from Bristol Temple Meads to Ashley Down, the arena and Henbury.
is needed now More than ever
The project, part of MetroWest phase 2, is reopening an old railway line with newly built stations.
As well as the 17,000-capacity YTL Arena, North Filton station will serve thousands of new houses planned for the neighbouring Filton Airfield, in a new development called Brabazon.
But it will take at least another four years before passengers can catch a train to North Filton.
Work on building the three new stations is being led by the West of England Combined Authority (WECA), and a planning application for North Filton train station has gone to South Gloucestershire council, which has not yet decided whether to grant planning permission.
Another issue is how often the trains will run, with initial plans for just one service an hour.
A spokesman for YTL said: “Responsibility for delivering the station sits with WECA and Network Rail. The station is due to open by mid-2026, however the combined authority team is currently looking at options for accelerating the work and we are working closely with them.
“YTL is working with Network Rail and Great Western Railway [GWR] on the frequency of trains, particularly on event days. We have recently submitted a revised planning application to South Gloucestershire Council to increase the number of units on the Brabazon development. This application is based upon a frequency of four trains per hour at peak times.”

YTL is building the 17,000-capacity arena at the Brabazon Hangars site in Filton – image: YTL Developments
A source at WECA said the delays to North Filton station were due to several design changes. These include needing to redesign a footbridge over the tracks, delays to the Henbury station—which impact North Filton as the two are being built together—and the need to do “value engineering and cost avoidance exercises” to keep project costs in control.
According to GWR, trains could eventually run every half hour to the new arena, but this depends on first getting the funding for the upgrades. The current infrastructure cannot run a 15-minute train service, vastly reducing how many passengers can travel to and from gigs.
Much further down the line, early-stage plans include completing the Henbury Loop by introducing a new service from North Filton and Henbury along an old existing railway to Avonmouth.
This would loop back to other Bristol stations like Clifton Down and Montpelier. A future mass transit system could also include a station at the Brabazon development.
But in the meantime, thousands of people travelling to the YTL Arena will not be able to get directly there by train. Three existing stations are nearby, at Parkway, Filton and Patchway, but these are all about half an hour from the arena on foot. Shuttle buses will also travel to the arena and a large car park will be built.
Despite the transport issues, mayor Marvin Rees recently called the arena “Europe’s most sustainable”, during his State of the City Address.
……………………………………
Read more: Mayor promises to steer ahead with underground railway
……………………………………
Before he came to office, the previous plan was to build a 12,000-capacity arena next to Temple Meads, a much larger and already existing train station.
He said: “When we came to office, we inherited the components of a plan to deliver a city centre arena, but began to discover the numbers were unravelling. We were faced with borrowing over £160m to build an arena with a 35-year break-even financial model with all the risk held by council taxpayers.”
Rees added: “If we had built the arena, we would have carried that debt and the new building into the lockdown. The financial and reputational consequences of that would have been considerable, to put it mildly. Instead, we now get homes, a hotel, conference centre and jobs on Temple Island, and the UK’s third largest and Europe’s most sustainable arena.”
Alex Seabrook is a local democracy reporter for Bristol
Main image: YTL Developments and Network Rail
Read next:
- Work to build new station to start one year after arena due to open
- Mayor promises to steer ahead with underground railway
- Delays to new transport works around arena could cause ‘chaos and calamity’
Listen to the latest Bristol24/7 Behind the Headlines podcast: